Recipient information | Input |
---|---|
Total number of customers served by utility / utilities supporting the project | 38,359 |
Total number of residential customers served by utility / utilities supporting the project | 34,280 |
Total number of commercial customers served by utility / utilities supporting the project | 4,079 |
Total number of industrial customers served by utility / utilities supporting the project | 0 |
Total number of AMI smart meters installed and operational prior to the SGIG/SGD program | 0 |
AMI smart meters installed and operational | Quantity* | Cost |
---|---|---|
Total | 0 | $6,549,604 |
Residential | 35,696 | |
Commercial | 4,304 | |
Industrial | 0 |
AMI smart meter features operational | Feature enabled | # of meters with feature |
---|---|---|
Interval reads | Yes | 40,000 |
Remote connection/disconnection | Yes | 16,000 |
Outage detection/reporting | Yes | 40,000 |
Tamper detection | Yes | 40,000 |
AMI communication networks and data systems | Description | Cost |
---|---|---|
Backhaul communications description | Elster Gatekeepers using CalAmp radios will comprise the backhaul network. CalAmp base stations will be integrated with the microwave radio platform covering the Navajo Nation footprint. Implementation of this solution is contingent upon acquisition of spectrum, which is slated for December, 2013. | $3,611,145 |
Meter communications network | Elster meter utilizes a mesh network topology to push data through the backhaul to reach the back office. | |
Head end server | Elster headend equipment is housed at the NTUA's Utility Operations Center and has been installed and is being tested. | $1,442,826 |
Meter data analysis system | ||
Other IT systems and applications |
Customer system communication networks | Description |
---|---|
Network characteristics within customer premise |
Pricing program | Customers with access | Customers enrolled | Description |
---|---|---|---|
Flat Rate | 148 | 148 | To help residential customers budget in advance for their utility bills, the Budget Payment Plan allows customers to avoid the burden of seasonal highs and lows by paying monthly averages year round. |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.