NRECA-KIUC
AMI smart meters installed and operational | Quantity* | Cost |
---|---|---|
Total | 0 | $209,020 |
Residential | 24,410 | |
Commercial | 4,038 | |
Industrial | 225 |
AMI smart meter features operational | Feature enabled | # of meters with feature |
---|---|---|
Interval reads | Yes | 28,673 |
Remote connection/disconnection | Yes | 26,859 |
Outage detection/reporting | Yes | 28,673 |
Tamper detection | Yes | 28,673 |
AMI communication networks and data systems | Description | Cost |
---|---|---|
Backhaul communications description | Fiber | $198 |
Meter communications network | RF Mesh | |
Head end server | $1,972 | |
Meter data analysis system | ||
Other IT systems and applications |
Web portal deployed and operational | Quantity* | Description |
---|---|---|
Customers with access to web portal | 28,498 | December 2013 Implementation |
Customers enrolled in web portal | 490 | MyMeter by Accelerated Innovations |
Customer systems installed and operational | Quantity* | Description | Cost |
---|---|---|---|
Communication networks and home area networks | N/A | N/A | |
In home displays | 937 | 3000 | $6,508 |
Energy management device | 0 | N/A | |
Direct load control devices | 0 | $3,746 | |
Programmable communicating thermostats | 0 | To be determined | $0 |
Smart appliances | 0 | $0 |
Customer system communication networks | Description |
---|---|
Network characteristics within customer premise |
Pricing program | Customers with access | Customers enrolled | Description |
---|---|---|---|
Flat Rate | 0 | 0 | Will be available once smart meters are installed. |
Net Metering | 0 | 0 |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.