AMI smart meters installed and operational | Quantity* | Cost |
---|---|---|
Total | 0 | $0 |
Residential | 0 | |
Commercial | 0 | |
Industrial | 0 |
AMI smart meter features operational | Feature enabled | # of meters with feature |
---|---|---|
Interval reads | No | 0 |
Remote connection/disconnection | No | 0 |
Outage detection/reporting | No | 0 |
Tamper detection | No | 0 |
AMI communication networks and data systems | Description | Cost |
---|---|---|
Backhaul communications description | $0 | |
Meter communications network | ||
Head end server | $0 | |
Meter data analysis system | ||
Other IT systems and applications |
Distributed energy resources | Quantity* | Capacity | Description | Cost |
---|---|---|---|---|
Distributed generation | 0 | 0 kW | This project is in the final phase Commissioning and Operations and is currently in commissioning. This project will be operating within the demand response area of ancillary services. It is behind the meter which eliminated the need for an interconnect agreement. | $0 |
Energy storage | 4 | 3,000 kW | $1,433,880 | |
Plug in electric vehicle charging points | 0 | 0 kW | $0 | |
Distributed energy resource interface | N/A | N/A | $1,262,068 |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.